Original Vietnamese content is translated by LaoDongAI
  • Home
  • Special Topic
  • Representatives responsible for caring for and protecting union members and workers
Perspective of the planned plan for the Trade Union social housing area in My Hao ward. Photo: Mai Huong
Perspective of the planned plan for the Trade Union social housing area in My Hao ward. Photo: Mai Huong

Hung Yen promotes Trade Union social housing project in My Hao ward

Mai Hương (báo lao động) 16/10/2026 09:28 (GMT+7)

Hung Yen - The Trade Union social housing project in My Hao ward is expected to have about 970 apartments for rent, striving to start construction in the second quarter of 2027.

On October 15, Hung Yen Provincial People's Committee worked with a working delegation of the Vietnam General Confederation of Labor (VGCL) to exchange and agree on contents related to the implementation of the project to invest in building social housing for trade unions in the province.

Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor and Mr. Lai Van Hoan - Vice Chairman of the Provincial People's Committee - co-chaired the working session.

Striving to start construction in Q2/2027

According to the Hung Yen Provincial Department of Construction, 2 Trade Union Facilities Zones are planned in the province, including: Trade Union Facilities Zone in Song An commune (now belonging to Vu Phuc ward) which is temporarily suspended and Trade Union Facilities Zone in Pho Noi A Industrial Park (now belonging to My Hao ward) with a scale of 32,822 m2.

For the Trade Union Facilities Area in Pho Noi A Industrial Park, it is being implemented by 2 component projects including: The Industrial Park Trade Union headquarters project associated with the Legal Consulting Center and cultural and sports infrastructure for workers, civil servants, and laborers, which has now completed site clearance; The social housing project for workers and laborers has not been approved.

According to a report by the Vietnam General Confederation of Labor, the project in My Hao ward has been cleared; the investment policy is expected to be adjusted in the direction of merging the two phases into the project "Trade Union Social Housing for Rent in Hung Yen", using Trade Union financial resources, in accordance with the provisions of the 2023 Housing Law.

 UBND tỉnh Hưng Yên làm việc với đoàn công tác Tổng Liên đoàn Lao động Việt Nam về triển khai dự án nhà ở xã hội Công đoàn.
Hung Yen Provincial People's Committee works with the working delegation of the Vietnam General Confederation of Labor on the implementation of the Trade Union social housing project. Photo: Mai Huong

Accordingly, the project includes 4 9-story buildings, about 970 apartments for rent, meeting the housing needs of about 3,200 people; and arranging parking areas, green trees, traffic, technical infrastructure and outdoor cultural and sports facilities, kindergartens...

For the project in Vu Phuc ward, the land for project implementation has not been cleared, does not have technical infrastructure and has not been allocated capital in the medium-term public investment plan for the period 2026 - 2030.

Ông Lê Văn Nghĩa - Phó Chủ tịch Tổng Liên đoàn Lao động Việt Nam phát biểu tại buổi làm việc.
Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor - spoke at the working session. Photo: Mai Huong

Vice President of the Vietnam General Confederation of Labor Le Van Nghia said that the Vietnam General Confederation of Labor will coordinate with the Hung Yen Provincial People's Committee and relevant agencies to review and complete procedures according to their authority, striving to start the project in My Hao ward in the second quarter of 2027, with a construction time of about 18 months, aiming to be completed by the end of 2028 or the first quarter of 2029.

Ông Lại Văn Hoàn - Phó Chủ tịch UBND tỉnh Hưng Yên phát biểu kết luận buổi làm việc. Ảnh: Mai Hương
Mr. Lai Van Hoan - Vice Chairman of Hung Yen Provincial People's Committee - delivered a concluding speech at the working session. Photo: Mai Huong

Meeting the housing needs of workers

Vice Chairman of Hung Yen Provincial People's Committee Lai Van Hoan emphasized that the project implementation in My Hao ward is of practical significance, contributing to supplementing a stable housing fund, meeting the housing needs of workers during their time working in the locality and continuing to serve other workers when needs change.

Bà Đỗ Thị Hương - Chủ tịch LĐLĐ tỉnh Hưng Yên phát biểu tại buổi làm việc. Ảnh: Mai Hương
Ms. Do Thi Huong - Chairwoman of Hung Yen Provincial Labor Federation - spoke at the working session. Photo: Mai Huong

Relevant departments and branches of the province coordinate to complete land allocation procedures and necessary conditions for project implementation. After having a land allocation decision, My Hao ward coordinates to notify and guide households to relocate crops and architectural structures on the land according to regulations, ensuring timely handover of land.

Along with that, review and identify plans to connect technical infrastructure outside the project area such as transport infrastructure, water supply, drainage, wastewater treatment and electricity supply, ensuring synchronization with the common infrastructure system of the area.

See the original here

Same category