Hanoi - Three river-crossing bridges and railways of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Component project 2.1 invests in the construction of a parallel road system (urban road) of Ring Road 4 through Hanoi with a total length of about 58.2km.

The route passes through 7 districts including Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

Recorded in package No. 8 - construction of a parallel road through Soc Son and Me Linh districts, after 21 months since the start of construction, the parallel road has revealed its shape.

Duong song hanh Vanh dai 4 doan qua huyen Me Linh (Ha Noi) dat khoang 70% khoi luong cong viec sau 21 thang tu thoi diem khoi cong. Phia xa la cau vuot thon Hau dang duoc xay dung. Anh: Huu Chanh
The parallel road of Ring Road 4 through Me Linh district (Hanoi) has reached about 70% of the workload after 21 months from the start of construction. In the distance is the Hau village overpass under construction. Photo: Huu Chanh

Speaking with Lao Dong, Mr. Nguyen Hoai Nam - Head of the Technical Department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - said that package No. 8 has a total length of about 23km, of which about 20km of parallel roads have been paved with asphalt.

Some sections on the route are being constructed with crushed stone by the contractor.

Trong anh la cau vuot duong sat Bac - Nam tuyen Ha Noi - Lao Cai dang duoc xay dung tren tuyen duong song hanh Vanh dai 4 doan qua Me Linh (Ha Noi). Anh: Huu Chanh
In the photo is the overpass of the North-South railway line Hanoi - Lao Cai under construction on the Ring Road 4 parallel road through Me Linh (Hanoi). Photo: Huu Chanh
Cau co 27 nhip voi chieu dai gan 590m, mat cat ngang moi ben 15m. Anh: Huu Chanh
The bridge has 27 spans with a length of nearly 590m, with a cross-section of 15m on each side. Photo: Huu Chanh

Package 8 also undertakes the construction of 3 overpasses on the route including the Ca Lo River overpass connecting Soc Son with Me Linh, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Of these, the railway overpass is the largest bridge built under package No. 8. The project is nearly 590m long with 27 spans on both sides, the width of the bridge deck is 15m on each side.

"2 weeks ago, the power line within the scope of the project was relocated. After the ground, the contractor conducted the construction of 4 bridges and the remaining 8 beats. It is expected that by June, the bridge will basically complete the construction.

The contractor is also ensuring the construction progress of the remaining 2 bridges in package 8, including Ca Lo bridge and Hau village bridge.

Cau vuot song Ca Lo noi huyen Soc Son va Me Linh da co ban hoan thanh cac hang muc chinh. Anh: Huu Chanh
The Ca Lo River overpass connecting Soc Son and Me Linh districts has basically completed the main items. Photo: Huu Chanh
Cong nhan dang thi cong hang muc lan can cau vuot song Ca Lo. Anh: Huu Chanh
Workers are constructing the railing of the Ca Lo River overpass. Photo: Huu Chanh

Regarding the progress of package No. 8, Mr. Nam said that up to this point, the contractor consortium has completed about 70% of the construction volume, ensuring progress compared to the plan.

According to Mr. Nguyen Hoai Nam, there are still 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh) that have not been handed over the project.

"With the sections that have cleared the ground, the contractor consortium is committed to completing the Ring Road 4 parallel road project through Me Linh and Soc Son in 2025" - Mr. Nam affirmed.