Bac Kan - At the construction site of the shoe and footwear factory in Huyen Tung Industrial Cluster, workers and machinery are speeding up construction, expected to be completed in the second quarter of 2025.

As a mountainous province with many difficulties, Bac Kan mainly develops agriculture and forestry, while industry is not strong. The export shoe processing factory in Huyen Tung Industrial Cluster (Bac Kan City) is one of the major production projects being completed.

The project started in June 2024, on a scale of 13 hectares with a total investment of 25 million USD (more than 600 billion VND), with a capacity of 10 million pairs of shoes/year.

The factory is expected to attract secondary investors when completed and put into operation, thereby creating jobs for about 5,000 local workers.

According to the reporter of Lao Dong Newspaper at the end of March 2025, after nearly 1 year of implementation, the factory project has basically been completed and is currently in the construction phase of the operator's house.

Du an nha may giay, dep co tong muc dau tu hon 600 ti dong, trien khai tai Cum cong nghiep Huyen Tung (TP Bac Kan) sap hoan thanh. Anh: Nguyen Hoan.
The shoe and footwear factory project with a total investment of more than 600 billion VND, deployed in Huyen Tung Industrial Cluster (Bac Kan City) is about to be completed. Photo: Nguyen Hoan.

At the construction site, workers and engineers are mobilized to construct important items. Machinery leveling, rolling the road, completing a series of technical infrastructure and other auxiliary items.

Talking with reporters, the project investor representative said that by March 2025, the two most important items, the factory and warehouse, had been completed, and a number of equipment and machinery lines had been installed.

Other technical infrastructure items such as transportation systems, water supply and drainage, and wastewater treatment have reached more than 90% of the workload.

"Contractors are focusing and urgently implementing the completion phase of some auxiliary items to prepare to put the plant into operation, expected in the second quarter of 2025," the investor's representative added.

Previously, Mr. Dinh Quang Tuyen - Permanent Vice Chairman of the People's Committee of Bac Kan province said that the factory project implemented at Huyen Tung Industrial Cluster is the project with the largest scale of labor use in the province.

"This is one of the very good opportunities to attract workers back to the locality, both to have jobs and to contribute to the economic and social development of the region," the provincial leader emphasized.

Some recorded images:

Sau gan 1 nam trien khai, du an nha may giay, dep da co ban hoan thien ha tang. Anh: Nguyen Hoan.
After nearly 1 year of implementation, the shoe and footwear factory project has basically completed the infrastructure. Photo: Nguyen Hoan.
Nha dieu hanh cung da xong phan tho. Anh: Nguyen Hoan.
The operator's house has also completed the rough construction. Photo: Nguyen Hoan.
Khu vuc nha xuong hien dai. Anh: Nguyen Hoan.
Modern factory area. Photo: Nguyen Hoan.
Cac cong nhan, may moc duoc huy dong tien hanh san gat, hoan thien cac hang muc cuoi cung. Anh: Nguyen Hoan.
Workers and machinery are mobilized to level and complete the final items. Photo: Nguyen Hoan.
Khu vuc thi cong duoc cang day, lap dat bien canh bao va huong dan nguoi, phuong tien tham gia giao thong de dam bao an toan, trach ach tac. Anh: Nguyen Hoan.
The construction area has been roped off, warning signs have been installed and people and vehicles have been instructed to participate in traffic to ensure safety and avoid congestion. Photo: Nguyen Hoan.

Read the original here

Same category