Revealing the route of the 10-lane road project in Hanoi after site clearance

HỮU CHÁNH (báo lao động) 24/06/2026 09:13 (GMT+7)

Hanoi - The Tay Thang Long road project, the section from Ring Road 3 to Van Tien Dung road, has basically completed site clearance, and the project route has been revealed.

The Tay Thang Long trunk road is about 34.17km long, starting point at Vo Chi Cong street, ending point intersecting National Highway 32, passing through 10 communes and wards.

The current investment status of the entire route is divided into 9 sections, including 3 sections that have been put into operation, 2 sections under construction, 1 section preparing to start construction and 3 sections under research and investment preparation.

To date, about 6.08km has been completed and put into operation; about 9km is under construction; preparations for the commencement of the Tay Thang Long - Ring Road 3 underpass, 0.92km long (expected in August 2026); and at the same time, preparations for investment in the remaining route sections are being implemented.

Đường Tây Thăng Long đoạn từ Vành đai 3 đến đường Văn Tiến Dũng (Hà Nội) đã cơ bản hoàn thành giải phóng mặt bằng sau nhiều năm vướng mắc. Ảnh: Sóng Hữu
Tay Thang Long road section from Ring Road 3 to Van Tien Dung road (Hanoi) has basically completed site clearance after many years of obstacles. Photo: Song Huu
Một số công trình trong phạm vi dự án đang được phá dỡ. Ảnh: Sóng Hữu
Some works within the project are being demolished. Photo: Song Huu

For the section from Ring Road 3 to Van Tien Dung road, it is more than 3.2km long, with a total investment of more than 2,300 billion VND, of which site clearance costs are about 1,673 billion VND.

The section from Ring Road 3 to Van Tien Dung street was started many years ago, but due to problems in site clearance, it is behind schedule.

It will not be until June 2026 that site clearance work will be basically completed.

According to Dong Ngac Ward People's Committee, to date, 100% of agricultural land has been cleared.

Regarding residential land, all 454 households have been counted and mobilized to hand over land. Many households have received compensation money. Demolition work is being implemented, expected to be completed in June 2026.

Regarding construction work, Dong Ngac Ward People's Committee said that the volume of the entire route has only reached about 65%. Some items such as bridges, drainage systems and technical trenches have been deployed, but the overall progress is still slow.

Một số đoạn đang trong quá trình thi công. Ảnh: Sóng Hữu
Some sections are under construction. Photo: Song Huu
Cầu bắc qua sông Nhuệ đã lộ diện hình hài. Ghi nhận chiều 23.6, tại đây không có hoạt động thi công. Ảnh: Sóng Hữu
The bridge across the Nhue River has revealed its shape. Recorded in the afternoon of June 23, there was no construction activity here. Photo: Song Huu
Nguyên vật liệu xây dựng tập kết trên cầu qua sông Nhuệ. Ảnh: Sóng Hữu
Construction materials are gathered on the bridge over the Nhue River. Photo: Song Huu
Hệ thống lan can cầu đã được lắp đặt. Ảnh: Sóng Hữu
The bridge railing system has been installed. Photo: Song Huu
Công trường dự án tiếp giáp với đường bờ Tây Sông Nhuệ. Ảnh: Sóng Hữu
The project site is adjacent to the West bank of the Nhue River. Photo: Song Huu
Đường Tây Thăng Long đoạn từ Vành đai 3 đến đường Văn Tiến Dũng có quy mô 10 làn xe. Ảnh: Sóng Hữu
Tay Thang Long road section from Ring Road 3 to Van Tien Dung road has a scale of 10 lanes. Photo: Song Huu

The section from Ring Road 3.5 to Dan Hoai canal (belonging to O Dien commune) is 5.8km long, with a total investment of 1,298 billion VND.

To date, the land area recovered for site clearance has reached over 95%; site clearance is expected to be completed in June 2026 and the project to be completed in the fourth quarter of 2026.

Regarding the Tay Thang Long road project, Politburo Member, Secretary of the Hanoi Party Committee Tran Duc Thang requested the Party Committee and People's Committee of the City to direct departments, branches, and localities to focus on accelerating the implementation progress of the entire route, ensuring synchronous investment and interconnection of the entire route to Ring Road 5 (Vinh Thinh bridge), striving to complete it in 2027.

Hanoi Party Secretary Tran Duc Thang also requested to urgently complete investment procedures for the remaining route sections; agreed to assign the City Traffic Construction Investment Project Management Board as the focal point for implementing the overall project.