Long Thanh airport fuel supply system worth 2,880 billion VND is about to be completed
Dong Nai - Package 4.9, Long Thanh airport fuel supply system has a contract value of more than 2,880 billion VND.
On April 14, according to information from Vietnam Airports Corporation (ACV), package 4.9, Long Thanh airport fuel supply system, the contractor consortium has mobilized 364 personnel and more than 70 machinery and equipment to deploy construction, the total value of the actual volume to date has reached about over 2,686 billion VND.
To ensure synchronization in operation and exploitation along with the passenger terminal project and other bidding packages, the contractor consortium strives to complete the construction milestones of the main items to ensure readiness to put the project into operation in June 2026.
In which, completing internal traffic roads, technical infrastructure, and landscape items before May 15; completing the completion of house items before April 30; trial operation of electrical - control system, technology system (pumps, valves, filters..), fire prevention and fighting in 2 months and washing pipelines in 3 months from the date of supplying 22kV power, water and fuel for washing...
Bidding package 4.9 - Long Thanh airport fuel supply system with a contract value of more than 2,880 billion VND started in October 2024.