Image of the 6-lane road about to open to traffic connecting 2 districts of Hanoi

hữu chánh (báo lao động) 08/04/2025 10:44 (GMT+7)

Hanoi - The road is more than 2.5km long, meeting 6 lanes, and is completing the final items, preparing to technically open to traffic after 27 months of construction.

Started in February 2023, the Le Quang Dao extended road construction project is preparing to reach the finish line.

This is a route that many people are looking forward to, because when completed, it will help shorten travel time between Nam Tu Liem and Ha Dong districts, reduce traffic pressure on routes in the area, and contribute to promoting the socio-economic development of the capital.

The project to build an extended Le Quang Dao road is 2.6km long, starting at the intersection of Le Quang Dao - Thang Long Avenue (Nam Tu Liem District), ending at Duong Noi Urban Area (Ha Dong District).

The total investment of the project is more than 700 billion VND, invested by the People's Committee of Nam Tu Liem District.

To implement the project, Nam Tu Liem district has reclaimed and cleared 123,351.5m2 of land, involving 364 households and 8 organizations, in the wards of Me Tri, Trung Van and Dai Mo.

According to the design, the route meets inter-regional road standards, with a design speed of 60 km/h. The typical cross-section is 40m, the section connecting to Thang Long Avenue (about 110m long) has a cross-section of 100m wide.

Previously, the 1.9km section from the Thang Long Avenue service road intersection to the end of the intersection with Dai Mo Street (Provincial Road 70) was basically completed and temporarily opened to traffic from January 22, helping people travel more conveniently.

According to the reporter of Lao Dong Newspaper, many machines and workers are being mobilized to construct the final items of the project (from the intersection of Provincial Road 70 to the area near Anland Lakeview apartment building).

The items being implemented include paving sidewalks, installing lighting systems, planting trees and completing miniatures along the route...

According to the representative of the Nam Tu Liem District Construction Investment Project Management Board, up to now, the project has basically completed the main items.

According to the contract signed between the investor and the contractor, the entire project will be completed in May 2025, after 27 months of construction.

Duong Le Quang Dao keo dai doan tu nut giao duong tinh 70 den nut giao duong gom Dai lo Thang Long dai 1,9km duoc thong xe hoi thang 1.2025. Anh: Huu Chanh
Le Quang Dao Street extended from the intersection of Provincial Road 70 to the intersection of Thang Long Avenue service road, 1.9km long, to be opened to traffic in January 2025. Photo: Huu Chanh
Doan con lai dai khoang 0,7km dang duoc nha thau gap rut thi cong hoan thien. Anh: Huu Chanh
The remaining section of about 0.7km is being urgently completed by the contractor. Photo: Huu Chanh
Duong Le Quang Dao doan qua khu do thi Louis City Dai Mo (Ha Noi) da hoan thanh tham nhua mat duong. Anh: Huu Chanh
Le Quang Dao Street through Louis City Dai Mo urban area (Hanoi) has completed asphalt pavement. Photo: Huu Chanh
Diem cuoi du an (doan gan chung cu Anland Lakeview) dang duoc nha thau thi cong hoan thien. Anh: Huu Chanh
The end point of the project (the section near Anland Lakeview apartment building) is being completed by the contractor. Photo: Huu Chanh
Hang muc lat da via he dang duoc cong nhan trien khai. Anh: Huu Chan
The sidewalk stone paving item is being deployed by workers. Photo: Huu Chan
Tieu canh duoc cong nhan trong o dai phan cach. Anh: Huu Chanh
Sub-sects are planted by workers in the median strip. Photo: Huu Chanh
May moc, cong nhan duoc huy dong day nhanh tien do thi cong du an. Anh: Huu Chanh
Machinery and workers are mobilized to speed up the project's construction progress. Photo: Huu Chanh
Bien chi dan duoc lap dat tren tuyen. Anh: Huu Chanh
Instructional signs are installed on the route. Photo: Huu Chanh
Mot doan via he da duoc thi cong hoan thien. Anh: Huu Chanh
A section of the sidewalk has been completed. Photo: Huu Chanh
He thong cay xanh duoc trong tren tuyen. Anh: Huu Chanh
A system of trees is planted on the route. Photo: Huu Chanh
Trong anh la nut giao duong Le Quang Dao keo dai va duong tinh 70. Du an du kien thong xe toan tuyen vao thang 5, giup ket noi giua quan Nam Tu Liem va Ha Dong duoc thuan loi. Anh: Huu Chanh
In the photo is the intersection of the extended Le Quang Dao road and Provincial Road 70. The project is expected to open to traffic in May, helping to facilitate the connection between Nam Tu Liem and Ha Dong districts. Photo: Huu Chanh