Bac Ninh plans to have a VND740 billion nursing home
Bac Ninh - The general hospital and nursing home project in Thuan Thanh ward has a total capital of 740 billion VND.
The People's Committee of Bac Ninh province has just issued a decision approving Nga Tu Ho General Hospital Company Limited as the investor to implement the investment project to build a general and nursing hospital.
Accordingly, Nga Tu Ho General Hospital Company Limited has a business code: 2301167486, first registered on February 25, 2021, and registered for the 6th change on October 6, 2025, issued by the Business Registration and Business Management Department, Department of Finance of Bac Ninh province.
Address: No. 5, Ben Ho area, Thuan Thanh ward, Bac Ninh province.
The total investment capital of the project is 740 billion VND. Of which, the investor's contributed capital is 150 billion VND, mobilized capital is 590 billion VND. Mobilized source: Borrowed from credit institutions. The capital mobilization progress is according to the project implementation progress.
Regarding project implementation progress, implementation of procedures on land, site clearance, environment, construction and other related legal procedures according to the provisions of law: 12 months from the date of competent authority's approval of the investor.
Put the project into operation: 36 months from the date of approval by the competent authority.
The project's operation period: 50 years (from the date the Investor is decided by the competent state agency to allocate land to implement the project).
It is known that the investment scale of hospitals and nursing homes is about 250 beds, including the following projects: general hospital area, nursing facility area; green campus; parking lot, internal traffic, yard...
The project implementation location is in Tram Lo and Thuan Thanh wards, Bac Ninh province.