Original Vietnamese content is translated by LaoDongAI
GENERAL INFORMATION WEBSITE
Member of the Party Central Committee, President of the Vietnam General Confederation of Labour Nguyen Anh Tuan speaks at the groundbreaking ceremony of Trade Union social housing in Yen Trung and Tam Da communes, Bac Ninh city. Photo: Huu Chanh
Member of the Party Central Committee, President of the Vietnam General Confederation of Labour Nguyen Anh Tuan speaks at the groundbreaking ceremony of Trade Union social housing in Yen Trung and Tam Da communes, Bac Ninh city. Photo: Huu Chanh

Commencement of Trade Union social housing in Bac Ninh, completed in 2029

CHÁNH PHƯƠNG (báo lao động) 17/11/2026 15:17 (GMT+7)

Bac Ninh - The Trade Union social housing project in Yen Trung and Tam Da communes has 6 10-story housing blocks with 810 apartments for rent, expected to be completed in July 2029.

On the morning of November 17, the Vietnam General Confederation of Labor (VGCL) organized the groundbreaking ceremony for the Trade Union social housing project in Yen Trung and Tam Da communes, Bac Ninh city.

Speaking at the groundbreaking ceremony, Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labour said that the Trade Union social housing project in Yen Trung and Tam Da communes, Bac Ninh city is invested by the Vietnam General Confederation of Labour with trade union financial capital according to the 2023 Housing Law.

The main items of the project include 6 10-story residential blocks, with a total construction floor area of 55,420 m2, with 810 closed rental apartments along with elevators and basic equipment and furniture (beds, wardrobes, kitchen cabinets...), meeting the essential living needs of workers and laborers.

s
Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor spoke at the groundbreaking ceremony. Photo: Huu Chanh

According to Mr. Nghia, when completed, Trade Union social housing will partially solve housing difficulties for union members and workers in Yen Trung and Tam Da communes in particular and Bac Ninh city in general, contributing to the completion of the target of the Project of 1 million apartments approved by the Government.

Speaking to direct at the groundbreaking ceremony, Mr. Nguyen Anh Tuan - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor requested the investor, supervision consulting unit and construction contractor to strictly control, avoid incurring off-budget costs and minimize the use of contingency funds.

Regarding the project progress, Mr. Nguyen Anh Tuan stipulated that the project must be completed and put into use before July 28, 2029 - to celebrate the 100th anniversary of the founding of the Vietnam Trade Union.

s
Delegates perform the groundbreaking ceremony. Photo: Huu Chanh

Faced with the fact that the project has up to 8 contractors in the construction consortium, he requested the investor and contractors to build an overall progress chart (framework) for the entire project instead of separating each item, and at the same time coordinate smoothly to avoid delays in the construction process.

At the same time, Chairman Nguyen Anh Tuan requested construction units and supervision consultants to put labor safety and environmental sanitation first.

In particular, workers and laborers at the construction site need to strictly comply with the law, respect local customs and traditions, and closely coordinate with local authorities.

The President of the Vietnam General Confederation of Labor noted that civil contractors need to strictly manage personnel, absolutely not to let situations occur that cause insecurity and social disorder, affecting the lives of local people.

He requested the People's Committee of Bac Ninh City and the Department of Construction to pay attention to supporting local adjustments to the design of works in accordance with the revised Housing Law expected to be passed by the National Assembly on November 21.

We hope that when the project is completed, it will create a truly quality living environment for workers and laborers to feel secure in working and contributing to the overall development of Bac Ninh city" - Chairman of the VGCL emphasized.

Mr. Nguyen Anh Tuan committed to drastically directing the investor to implement the project according to the set goals, contributing to completing the technical housing infrastructure of Bac Ninh city as well as social infrastructure in industrial parks in Tam Da and Yen Trung communes.