Ho Chi Minh City Ring Road 3 through Dong Nai province has technically opened 5 km of the highway. Photo: HAC
Ho Chi Minh City Ring Road 3 through Dong Nai province has technically opened 5 km of the highway. Photo: HAC

Ho Chi Minh City Ring Road 3 through Dong Nai construction has reached more than 63%

HÀ ANH CHIẾN (báo lao động) 06/01/2026 14:29 (GMT+7)

Dong Nai - Ho Chi Minh City Ring Road 3 from Ben Luc - Long Thanh Expressway to Nhon Trach Bridge has a total investment of 2,584 billion VND, and has completed more than 63%.

On January 5, according to information from the Dong Nai Province Construction Investment Project Management Board, Component Project 3, Ho Chi Minh City Ring Road 3 Project through the province is implementing 3 main construction packages with an output of more than 63% of the contract value.

Component project 3 of the Ho Chi Minh City Ring Road 3 project is over 11 km long, with the starting point intersecting with the Ben Luc - Long Thanh expressway, the end point intersecting with Mo B on Nhon Trach bridge, with a total investment of 2,584 billion VND.

In particular, the project will invest in the construction of 5 km of expressway connecting with Component Project 1A, Ho Chi Minh City Ring Road 3 project at the intersection with Provincial Road 25B. Currently, the 5 km long main expressway section of the project has been technically opened to traffic.

In addition, the project will also invest in the construction of parallel roads along both sides of the expressway, and has so far completed 100% of the filling of K95 road, crushed stone aggregate...